Energy Projects Near You

Solar, wind and battery projects near Robertsbridge (TN32)

8 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TN32 (Rother): 1 is waiting for a planning decision, 4 approved but not yet running. The largest live scheme is Park Pale House, Mountfield Lane Solar Panel Array (1.2 MW solar farm, approved on 4 April 2024, not yet built), 3.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8projects within 10 km
1awaiting a decision
4approved, not running
0operational

Projects within 10 km of TN32

Projects of 1 MW and more (1)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Park Pale House, Mountfield Lane Solar Panel Arraysolar farmsolar farm1.2approved, not builtupdated May 2024Feb 2024granted Apr 2024May 2024Rother3.0
Smaller schemes under 1 MW, mostly rooftop solar (7)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Darvell Bruderhof Community, Brightling Roadsolar farmsolar farm0.5approved, not built may be out of dateupdated Dec 2022Sep 2022granted Nov 2022Dec 2022Rother1.9
Northpoint, Compass Parkrooftop solarrooftop solar0.2refusedupdated Jan 2026Jun 2025refused Aug 2025Jan 2026Rother2.1
Robertsbridge Works Solar Panelssolar farmsolar farm—approved, not built may be out of dateupdated Oct 2021Jun 2021granted Sep 2021Oct 2021Rother4.0
Marley Lanerooftop solarrooftop solar0.2approved, not builtupdated Jan 2024Nov 2023granted Jan 2024Jan 2024Rother7.1
Lower Ellenden Farm, Water Lanesolar farmsolar farm—refusedupdated May 2025Jul 2024refused May 2025May 2025Tunbridge Wells8.8
Lower Ellenden Farm, Water Lanebattery storagebattery storage—refusedupdated May 2025Jul 2024refused May 2025May 2025Tunbridge Wells8.8
Dale Hill Hotel & Golf Club, Dale Hill - Ground Mounted Solar Panelssolar farmsolar farm0.3application submittedupdated Oct 2025Sep 2025—Oct 2025Rother9.1

Distance from the average position of the TN32 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm513012
Rooftop solar201010.2
Battery storage100010

MW in pipeline: pending, approved and under-construction capacity.

How Rother decides solar, wind and battery applications

ApplicationsRotherUK
Decided applications (solar, wind, battery)1510,236
Refused4 (27%)19%
Solar refused4 of 1312%
Battery storage refused0 of 216%
Median time from submission to decision11.1 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

All projects in Rother

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near TN32, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.