Energy Projects Near You

Solar, wind and battery projects near Watford (WD17)

36 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of WD17 (Watford): 6 are waiting for a planning decision, 17 approved but not yet running, 4 operational. The largest live scheme is Hilfield Lane, Aldenham (170 MW battery storage, approved on 16 January 2026, not yet built), 4.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

36projects within 10 km
6awaiting a decision
17approved, not running
4operational

Projects within 10 km of WD17

Projects of 1 MW and more (9)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Langleybury Film Hubrooftop solarrooftop solar3application submitted may be out of dateupdated Dec 2022Oct 2022—Dec 2022Three Rivers3.9
Elstree Substation, Hilfield Lanebattery storagebattery storage400application withdrawnupdated Nov 2024Nov 2023—Nov 2024Hertsmere4.4
Hilfield Lane, Aldenhambattery storagebattery storage170approved, not builtupdated Feb 2026Feb 2025granted Jan 2026Feb 2026Hertsmere4.7
Hilfield Solar arrays & Battery storagesolar farmsolar farm49.9application withdrawnupdated Jul 2024May 2022—Jul 2024Hertsmere4.7
David Lloyd Leisure, Ducks Hill Roadrooftop solarrooftop solar1refusedupdated Jul 2023Jun 2023—Jul 2023Hillingdon6.2
Butterfly Lane, Elstree BESSbattery storagebattery storage99.9appeal lodgedupdated Jun 2026Jul 2025—Jun 2026Hertsmere6.5
Beechtree Junction, Potters Crouchsolar farmsolar farm49.9application submittedupdated Aug 2025Jul 2025—Aug 2025St Albans8.3
Bell Lane Solar Farmsolar farmsolar farm1refusedupdated Dec 2015Aug 2015refused Nov 2015Dec 2015Hertsmere9.2
Elstree Film And TV Studios, Shenley Roadrooftop solarrooftop solar3operationalupdated Sep 2023Feb 2023—Sep 2023Hertsmere9.4
Smaller schemes under 1 MW, mostly rooftop solar (27)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Tesco Stores Limited, Lower High Streetrooftop solarrooftop solar0.4approved, not builtupdated Mar 2025Nov 2024granted Jan 2025Mar 2025Watford1.9
David Lloyd Leisure Club, Hartspring Lanerooftop solarrooftop solar0.3approved, not builtupdated Sep 2025Jul 2025granted Sep 2025Sep 2025Hertsmere2.8
C P House, Otterspool Wayrooftop solarrooftop solar0.3approved, not builtupdated Dec 2022Oct 2022granted Dec 2022Dec 2022Hertsmere2.8
Kingsway North Orbital Roadrooftop solarrooftop solar0.2approved, not builtupdated Feb 2022Jan 2022granted Mar 2022Feb 2022Watford3.2
Woodside Leisure Centrerooftop solarrooftop solar0.3operationalupdated Mar 2025Dec 2024granted Jan 2025Mar 2025Watford3.6
York House School, Sarratt Roadrooftop solarrooftop solar0.3application withdrawnupdated Jan 2026Sep 2025—Jan 2026Three Rivers3.7
Rickmansworth School, Croxley Greenrooftop solarrooftop solar0.2approved, not builtupdated Feb 2023Dec 2022granted Feb 2023Feb 2023Three Rivers4.0
Hilfield Solar arrays & Battery storagebattery storagebattery storage—application withdrawnupdated Jul 2024May 2022—Jul 2024Hertsmere4.7
Royal Masonic School, Rickmansworth Parkrooftop solarrooftop solar0.1application submittedApr 2026——Three Rivers5.0
The Tropical Marine Centre, Solesbridge Lanerooftop solarrooftop solar0.2approved, not builtupdated Nov 2023Sep 2023granted Nov 2023Nov 2023Three Rivers6.1
Mount Vernon Hospitalrooftop solarrooftop solar—operationalupdated Jan 2022Jul 2021granted Nov 2021Jan 2022Hillingdon6.1
Northwood College, Maxwell Roadrooftop solarrooftop solar—approved, not builtupdated Jun 2023May 2023granted Jul 2023Jun 2023Hillingdon6.2
Northwood Health And Racquet Club, Ducks Hill Roadrooftop solarrooftop solar0.3application submitted may be out of dateupdated Aug 2023Jul 2023—Aug 2023Hillingdon6.3
Centennial Park, Centennial Avenuerooftop solarrooftop solar0.2approved, not builtupdated Mar 2025Dec 2024granted Feb 2025Mar 2025Hertsmere7.0
Aspire Leisure Centre, Wood Lanerooftop solarrooftop solar0.2refusedupdated Nov 2024Jul 2024refused Sep 2024Nov 2024Harrow7.6
Headstone Lanerooftop solarrooftop solar0.6approved, not builtupdated Nov 2024Oct 2023refused Sep 2024Nov 2024Harrow8.0
Sainsburys, The Broadwayrooftop solarrooftop solar0.2refusedupdated Apr 2026Dec 2025refused Feb 2026Apr 2026Harrow8.3
Micro House, Bury Street Solar Arraysrooftop solarrooftop solar—approved, not builtupdated May 2025Mar 2025granted Apr 2025May 2025Hillingdon8.6
Bullsland Farmsolar farmsolar farm0.3approved, not built may be out of dateupdated Feb 2022May 2021granted Jan 2022Feb 2022Three Rivers9.1
The End Of Taransey, Taransaybattery storagebattery storage0.2approved, not builtupdated Jul 2025Feb 2025granted Jul 2025Jul 2025Dacorum9.1
Elstree Film And TV Studios, Shenley Road Solar Panels And ASHPsrooftop solarrooftop solar—application withdrawnupdated May 2023Feb 2022—May 2023Hertsmere9.4
London Road Retail Park, Unit Arooftop solarrooftop solar0.1approved, not builtupdated May 2026Jan 2026granted Apr 2026May 2026Dacorum9.6
The Snowcentre, St Albans Hillrooftop solarrooftop solar0.8approved, not builtupdated May 2024Apr 2024granted May 2024May 2024Dacorum9.7
St Albans Retail Park, Griffiths Wayrooftop solarrooftop solar0.8approved, not builtupdated Oct 2023Aug 2023granted Oct 2023Oct 2023St Albans9.7
The Range, Graham Closerooftop solarrooftop solar0.5approved, not builtupdated Jul 2024May 2024granted Jul 2024Jul 2024St Albans9.7
Westminster Lodge Leisure Centrerooftop solarrooftop solar0.2application submitted may be out of dateupdated Mar 2022Mar 2022—Mar 2022St Albans9.9
Aylett Nurseriesrooftop solarrooftop solar—operationalupdated Aug 2023——Aug 2023St Albans9.9

Distance from the average position of the WD17 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm4110150.2
Rooftop solar27414438.2
Battery storage51200270

MW in pipeline: pending, approved and under-construction capacity.

How Watford decides solar, wind and battery applications

Watford has 3 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.

All projects in Watford

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near WD17, 4 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.