Energy Projects Near You

Aberarder Wind Farm (49.9 MW)

Aberarder Wind Farm is a 49.9 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 March 2023; the record was last updated on 17 August 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWwind farm
under constructionstatus in REPD
17 August 2023record last updated
Scotlandcouncil area

Planning timeline

DateStage
3 March 2015Application submitted
19 April 2016Refused by the planning authority
14 July 2016Appeal lodged
7 April 2017Planning permission granted
7 April 2017Appeal allowed
1 March 2023Construction started

Project details

Technology
wind farm
Capacity
49.9 MW
Status (REPD)
under construction
Record last updated
17 August 2023
Operator or applicant
Scottish & Southern Energy
Planning authority
Highland
Planning application reference
15/00737/FUL
Appeal reference
PPA-270-2158
Turbines
12
Turbine height
130 m
Address (REPD)
Land 4.5km South East Of Aberarder House Aberarder Inverness
Council area (by location)
not known
Time to decision
109 weeks
Contracts for Difference
AR5
REPD reference
3371

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Dunmaglass Wind Farmwind farm94operational1.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.2569, -4.2422).