Dunmaglass Wind Farm (94 MW)

Dunmaglass Wind Farm is a 94 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 13 September 2016; the record was last updated on 27 November 2017. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

94 MWwind farm
operationalstatus in REPD
27 November 2017record last updated
Highlandcouncil area

Planning timeline

DateStage
11 February 2005Application submitted
29 December 2010Section 36 consent granted (Scottish Ministers)
1 June 2014Construction started
13 September 2016Operational

Project details

Technology
wind farm
Capacity
94 MW
Status (REPD)
operational
Record last updated
27 November 2017
Operator or applicant
Scottish and Southern Energy (SSE)
Planning authority
Scottish Government (S36)
Planning application reference
not recorded
Turbines
33
Address (REPD)
Dunmaglass, Highlands, SW of Inverness
Council area (by location)
Highland
Time to decision
307 weeks
REPD reference
4118

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Aberarder Wind Farmwind farm49.9under construction1.0
Corriegarthwind farm69.5operational9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.2515, -4.2558).