Corriegarth (69.5 MW wind farm)

Corriegarth is a 69.5 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 September 2016; the record was last updated on 29 August 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

69.5 MWwind farm
operationalstatus in REPD
29 August 2017record last updated
Scotlandcouncil area

Planning timeline

DateStage
15 July 2007Application submitted
2 April 2015Planning permission granted
8 May 2015Construction started
30 September 2016Operational

Project details

Technology
wind farm
Capacity
69.5 MW
Status (REPD)
operational
Record last updated
29 August 2017
Operator or applicant
Greencoat Capital
Planning authority
Highland
Planning application reference
07/00673/FULIN
Turbines
23
Turbine height
120 m
Address (REPD)
Near Gorthleck , Inverness-shire
Council area (by location)
not known
Time to decision
403 weeks
REPD reference
4664

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Dunmaglass Wind Farmwind farm94operational9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.1901, -4.3596).