Energy Projects Near You

Solar, wind and battery projects near Drumnadrochit (IV63)

6 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of IV63 (Highland): 3 are waiting for a planning decision, 2 approved but not yet running. The largest live scheme is Loch Liath Wind Farm (85 MW wind farm, application submitted on 28 April 2023, no decision recorded; REPD status may be out of date), 3.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6projects within 10 km
3awaiting a decision
2approved, not running
0operational

Projects within 10 km of IV63

Projects of 1 MW and more (6)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Loch Liath Wind Farmwind farmwind farm85application submitted may be out of dateupdated Sep 2022Apr 2023—Sep 2022Highland3.7
Burnside Bhlaraidh - Chrathaich Wind Farmwind farmwind farm70approved, not builtupdated Jan 2026Jul 2023granted May 2025Jan 2026Highland4.4
Cnoc an Eas Wind Farmwind farmwind farm44.2refused on appealupdated Jun 2017Jul 2015refused May 2016Jun 2017Highland7.9
Cnoc Farasd Wind Farmwind farmwind farm28.8application submittedupdated Jan 2026Dec 2025—Jan 2026Highland8.7
Cnoc Farasd Wind Farmbattery storagebattery storage15application submittedupdated Jan 2026Dec 2025—Jan 2026Highland8.7
Bhlaraidh Wind Farm Extensionwind farmwind farm84approved, not builtupdated Feb 2025Aug 2021granted Aug 2022Feb 2025Highland10.0

Distance from the average position of the IV63 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm52201268
Battery storage1100015

MW in pipeline: pending, approved and under-construction capacity.

How Highland decides solar, wind and battery applications

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

All projects in Highland

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near IV63, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.