Energy Projects Near You

Solar, wind and battery projects near Fort Augustus (PH32)

7 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PH32 (Highland): 2 approved but not yet running, 2 operational. The largest live scheme is Tomchrasky Estate Wind farm (84 MW wind farm, approved on 6 May 2025, not yet built), 9.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7projects within 10 km
0awaiting a decision
2approved, not running
2operational

Projects within 10 km of PH32

Projects of 1 MW and more (7)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Culachy Wind Farmwind farmwind farm57.6refusedupdated Jun 2026Nov 2023refused Mar 2026Jun 2026Highland1.5
Culachy Wind Farmbattery storagebattery storage10refusedupdated Jun 2026Nov 2023refused Mar 2026Jun 2026Highland1.5
Torrdhuin, Auchteraw Battery Storage Facilitybattery storagebattery storage49.9operationalupdated Sep 2025Nov 2020granted Mar 2021Sep 2025Highland3.3
Auchteraw Energy Storagebattery storagebattery storage20application withdrawnupdated Jan 2023Dec 2019—Jan 2023Highland3.3
Tomchrasky Estate Wind farmwind farmwind farm84approved, not builtupdated Jul 2025Nov 2022granted May 2025Jul 2025Highland9.3
Tomchrasky Estate Wind farmbattery storagebattery storage50approved, not builtupdated Jul 2025Nov 2022granted May 2025Jul 2025Highland9.3
Stronelairg Wind Farmwind farmwind farm228operationalupdated Jan 2019Jun 2012granted Jun 2014Jan 2019—9.7

Distance from the average position of the PH32 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm3011184
Battery storage4011150

MW in pipeline: pending, approved and under-construction capacity.

How Highland decides solar, wind and battery applications

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

All projects in Highland

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.