Stronelairg Wind Farm (228 MW)

Stronelairg Wind Farm is a 228 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 11 December 2018; the record was last updated on 2 January 2019. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

228 MWwind farm
operationalstatus in REPD
2 January 2019record last updated
Scotlandcouncil area

Planning timeline

DateStage
29 June 2012Application submitted
6 June 2014Section 36 consent granted (Scottish Ministers)
20 April 2017Construction started
11 December 2018Operational

Project details

Technology
wind farm
Capacity
228 MW
Status (REPD)
operational
Record last updated
2 January 2019
Operator or applicant
Scottish and Southern Energy (SSE)
Planning authority
Scottish Government (S36)
Planning application reference
EC00005242
Turbines
66
Turbine height
135 m
Address (REPD)
located approximately 11 kilometres to the south-east of Fort Augustus
Council area (by location)
not known
Time to decision
101 weeks
REPD reference
4597

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Dell Wind Farm 2wind farm59.4application submitted2.7
Cloiche Wind Farmwind farm125approved, not built6.7
Culachy Wind Farmwind farm57.6refused8.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.1269, -4.5264).