Energy Projects Near You

Torrdhuin, Auchteraw Battery Storage Facility (49.9 MW)

Torrdhuin, Auchteraw Battery Storage Facility is a 49.9 MW battery storage project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 22 August 2025; the record was last updated on 22 September 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
operationalstatus in REPD
22 September 2025record last updated
Highlandcouncil area

Planning timeline

DateStage
18 November 2020Application submitted
9 March 2021Planning permission granted
25 September 2023Construction started
22 August 2025Operational

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
operational
Record last updated
22 September 2025
Operator or applicant
Field Energy
Planning authority
Highland
Planning application reference
20/04565/FUL
Address (REPD)
Land 325M SW Of Torrdhuin
Council area (by location)
Highland
Time to decision
16 weeks
REPD reference
8096

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Auchteraw Energy Storagebattery storage20application withdrawn<0.1
Culachy Wind Farmwind farm57.6refused4.4
Millennium Eastwind farm49.6application submitted7.5
Tomchrasky Estate Wind farmwind farm84approved, not built7.6
Millennium Extension IIwind farm15operational9.6
Millennium Windfarmwind farm40operational9.6
Millennium Extensionwind farm10operational9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.1297, -4.7316).