Millennium Windfarm (40 MW)

Millennium Windfarm is a 40 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 July 2008; the record was last updated on 26 April 2010.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40 MWwind farm
operationalstatus in REPD
26 April 2010record last updated
Highlandcouncil area

Planning timeline

DateStage
1 December 2003Application submitted
1 April 2005Planning permission granted
1 June 2006Construction started
15 July 2008Operational

Project details

Technology
wind farm
Capacity
40 MW
Status (REPD)
operational
Record last updated
26 April 2010
Operator or applicant
Renewable Development Company (RDC) Scotland (Ltd) for FALCK RENEWABLES
Planning authority
Highland
Planning application reference
03/00505/FULL
Turbines
16
Turbine height
125 m
Address (REPD)
Millennium Windfarm on The Achlain and Invergarry amd Aberchalder Estates Glengarry Invergarry Inverness-Shire (nr Glen Moriston Fort Augustus)
Council area (by location)
Highland
Time to decision
70 weeks
REPD reference
4682

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Millennium Extension IIwind farm15operational<0.1
Millennium Extensionwind farm10operational0.7
Millennium Eastwind farm49.6application submitted3.7
Tomchrasky Estate Wind farmwind farm84approved, not built3.8
Beinneun II Windfarmwind farm137application submitted6.3
Beinneun Windfarm Extensionwind farm23.8operational8.3
Beinneunwind farm85operational8.3
Bunloinn Wind Farmwind farm66.6approved, not built8.6
Auchteraw Energy Storagebattery storage20application withdrawn9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.1552, -4.8836).