Millennium Extension (10 MW wind farm)

Millennium Extension is a 10 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 December 2008; the record was last updated on 10 May 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWwind farm
operationalstatus in REPD
10 May 2016record last updated
Highlandcouncil area

Planning timeline

DateStage
10 March 2007Application submitted
12 January 2008Planning permission granted
13 January 2008Construction started
1 December 2008Operational

Project details

Technology
wind farm
Capacity
10 MW
Status (REPD)
operational
Record last updated
10 May 2016
Operator or applicant
West Coast Energy /Falck Renewables
Planning authority
Highland
Planning application reference
not recorded
Turbines
4
Turbine height
125 m
Address (REPD)
Millennium Windfarm on The Achlain and Invergarry amd Aberchalder Estates Glengarry Invergarry Inverness-Shire
Council area (by location)
Highland
Time to decision
44 weeks
REPD reference
3598

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Millennium Extension IIwind farm15operational0.7
Millennium Windfarmwind farm40operational0.7
Millennium Eastwind farm49.6application submitted3.5
Tomchrasky Estate Wind farmwind farm84approved, not built4.5
Beinneun II Windfarmwind farm137application submitted5.7
Beinneun Windfarm Extensionwind farm23.8operational7.5
Beinneunwind farm85operational7.5
Bunloinn Wind Farmwind farm66.6approved, not built8.0
Torrdhuin, Auchteraw Battery Storage Facilitybattery storage49.9operational9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.1502, -4.8912).