Millennium Extension II (15 MW wind farm)

Millennium Extension II is a 15 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 April 2011; the record was last updated on 5 May 2011. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15 MWwind farm
operationalstatus in REPD
5 May 2011record last updated
Highlandcouncil area

Planning timeline

DateStage
6 January 2009Application submitted
10 August 2009Section 36 consent granted (Scottish Ministers)
1 April 2010Construction started
1 April 2011Operational

Project details

Technology
wind farm
Capacity
15 MW
Status (REPD)
operational
Record last updated
5 May 2011
Operator or applicant
West Coast Energy Ltd/Falck Renewables
Planning authority
Scottish Government (S36)
Planning application reference
not recorded
Turbines
6
Address (REPD)
Millennium Windfarm, on The Achlain and Invergarry amd Aberchalder Estates, Glengarry Invergarry, Inverness-Shire, (nr Glen Moriston, Fort Augustus)
Council area (by location)
Highland
Time to decision
31 weeks
REPD reference
2723

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Millennium Windfarmwind farm40operational<0.1
Millennium Extensionwind farm10operational0.7
Millennium Eastwind farm49.6application submitted3.7
Tomchrasky Estate Wind farmwind farm84approved, not built3.8
Beinneun II Windfarmwind farm137application submitted6.3
Beinneun Windfarm Extensionwind farm23.8operational8.3
Beinneunwind farm85operational8.3
Bunloinn Wind Farmwind farm66.6approved, not built8.6
Auchteraw Energy Storagebattery storage20application withdrawn9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.1552, -4.8836).