Energy Projects Near You

Tomchrasky Estate Wind farm (84 MW)

Tomchrasky Estate Wind farm is an 84 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 6 May 2025, not yet built; the record was last updated on 1 July 2025. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

84 MWwind farm
approved, not builtstatus in REPD
1 July 2025record last updated
Highlandcouncil area

Planning timeline

DateStage
21 November 2022Application submitted
6 May 2025Section 36 consent granted (Scottish Ministers)
6 May 2028Permission due to expire (unless work starts)

Project details

Technology
wind farm
Capacity
84 MW
Status (REPD)
approved, not built
Record last updated
1 July 2025
Operator or applicant
E Power Limited
Planning authority
Scottish Government (S36)
Planning application reference
ECU00004663
Turbines
14
Turbine height
185 m
Address (REPD)
900m Ne/O Beinn An T-Sidhein Dalchreichart
Council area (by location)
Highland
Time to decision
128 weeks
REPD reference
8364

The scheme also includes 50 MW of battery storage, recorded separately in REPD (approved, not built).

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Millennium Windfarmwind farm40operational3.8
Millennium Extension IIwind farm15operational3.8
Millennium Extensionwind farm10operational4.5
Millennium Eastwind farm49.6application submitted5.5
Auchteraw Energy Storagebattery storage20application withdrawn7.6
Torrdhuin, Auchteraw Battery Storage Facilitybattery storage49.9operational7.6
Beinneun II Windfarmwind farm137application submitted9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.1731, -4.8292).