Cnoc an Eas Wind Farm (44.2 MW)

Cnoc an Eas Wind Farm is a 44.2 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 2 June 2017; the record was last updated on 29 June 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

44.2 MWwind farm
refused on appealstatus in REPD
29 June 2017record last updated
Highlandcouncil area

Planning timeline

DateStage
15 July 2015Application submitted
9 May 2016Refused by the planning authority
6 July 2016Appeal lodged
2 June 2017Appeal refused

Project details

Technology
wind farm
Capacity
44.2 MW
Status (REPD)
refused on appeal
Record last updated
29 June 2017
Operator or applicant
Force 9 Energy
Planning authority
Highland
Planning application reference
15/02758/FUL
Appeal reference
PPA-270-2155
Turbines
13
Turbine height
137 m
Address (REPD)
Land 2265m North West of Achratagan Balnain Drumnadrochit
Council area (by location)
Highland
Time to decision
43 weeks
REPD reference
4807

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Cnoc Farasd Wind Farmwind farm28.8application submitted1.7
Loch Liath Wind Farmwind farm85application submitted8.7
Burnside Bhlaraidh - Chrathaich Wind Farmwind farm70approved, not built9.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.3599, -4.6175).