Bhlaraidh Wind Farm Extension (84 MW)

Bhlaraidh Wind Farm Extension is an 84 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 30 August 2022, not yet built; the record was last updated on 3 February 2025. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

84 MWwind farm
approved, not builtstatus in REPD
3 February 2025record last updated
Highlandcouncil area

Planning timeline

DateStage
16 August 2021Application submitted
30 August 2022Section 36 consent granted (Scottish Ministers)
30 August 2028Permission due to expire (unless work starts)

Project details

Technology
wind farm
Capacity
84 MW
Status (REPD)
approved, not built
Record last updated
3 February 2025
Operator or applicant
SSE Renewables
Planning authority
Scottish Government (S36)
Planning application reference
ECU00001900
Turbines
15
Turbine height
180 m
Address (REPD)
Land adjacent to operational Blaraidh Wind Farm, near Invermoriston
Council area (by location)
Highland
Time to decision
54 weeks
Contracts for Difference
AR5
REPD reference
7473

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Bhlaraidh (previously Balmacaan)wind farm110operational6.0
Glenurquhart and Strathglass Wind Farm projectwind farm10operational6.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.2514, -4.6618).