Glenurquhart and Strathglass Wind Farm project (10 MW)
Glenurquhart and Strathglass Wind Farm project is a 10 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 19 April 2013; the record was last updated on 10 May 2013.
10 MWwind farm
operationalstatus in REPD
10 May 2013record last updated
Highlandcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 12 May 2010 | Application submitted |
| 18 November 2010 | Planning permission granted |
| 1 August 2012 | Construction started |
| 19 April 2013 | Operational |
Project details
- Technology
- wind farm
- Capacity
- 10 MW
- Status (REPD)
- operational
- Record last updated
- 10 May 2013
- Operator or applicant
- Corrimony Energy Ltd & Soirbheas
- Planning authority
- Highland
- Planning application reference
- 10/02132/FUL
- Turbines
- 5
- Address (REPD)
- Hill Ground At Corrimony Farm, Glenurquhart, Inverness
- Council area (by location)
- Highland
- Time to decision
- 27 weeks
- REPD reference
- 3746
Who decides
| Applications | Highland | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 160 | 10,236 |
| Refused | 68 (42%) | 19% |
| Solar refused | 0 of 15 | 12% |
| Onshore wind refused | 61 of 114 | 45% |
| Battery storage refused | 7 of 31 | 16% |
| Median time from submission to decision | 52.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 20 / 20 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Beinn Mhor | wind farm | 21 | refused on appeal | 4.8 |
| Kerrow Farm | battery storage | 20 | application withdrawn | 5.9 |
| Bhlaraidh Wind Farm Extension | wind farm | 84 | approved, not built | 6.2 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.2791, -4.7511).