Beinn Mhor (21 MW wind farm)

Beinn Mhor is a 21 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 9 July 2015; the record was last updated on 15 July 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

21 MWwind farm
refused on appealstatus in REPD
15 July 2015record last updated
Highlandcouncil area

Planning timeline

DateStage
1 May 2014Application submitted
23 February 2015Appeal lodged
9 July 2015Refused by the planning authority
9 July 2015Appeal refused

Project details

Technology
wind farm
Capacity
21 MW
Status (REPD)
refused on appeal
Record last updated
15 July 2015
Operator or applicant
WPD Beinn Mhor
Planning authority
Highland
Planning application reference
14/01731/FUL
Appeal reference
PPA-270-2120
Turbines
7
Address (REPD)
Guisachan, Tomich, Strathglass
Council area (by location)
Highland
Time to decision
62 weeks
REPD reference
4340

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Kerrow Farmbattery storage20application withdrawn4.2
Glenurquhart and Strathglass Wind Farm projectwind farm10operational4.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.295, -4.8245).