Energy Projects Near You

Kerrow Farm (20 MW battery storage)

Kerrow Farm is a 20 MW battery storage project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 12 June 2019; the record was last updated on 12 June 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWbattery storage
application withdrawnstatus in REPD
12 June 2019record last updated
Highlandcouncil area

Planning timeline

DateStage
1 March 2019Application submitted
12 June 2019Application withdrawn

Project details

Technology
battery storage (stand-alone storage)
Capacity
20 MW
Status (REPD)
application withdrawn
Record last updated
12 June 2019
Operator or applicant
Shires Hamilton
Planning authority
Highland
Planning application reference
19/00704/FUL
Address (REPD)
Land 690M SW Of Balnabruich, Cannich, Kerrow Farm, Beauly, Highlands
Council area (by location)
Highland
REPD reference
7353

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Beinn Mhorwind farm21refused on appeal4.2
Glenurquhart and Strathglass Wind Farm projectwind farm10operational5.9
Cnoc Farasd Wind Farmwind farm28.8application submitted9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.3275, -4.7906).