Acharn Forest (9.9 MW battery storage)

Acharn Forest is a 9.9 MW battery storage project in Stirling, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 10 January 2024, not yet built; the record was last updated on 16 January 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9.9 MWbattery storage
approved, not builtstatus in REPD
16 January 2024record last updated
Stirlingcouncil area

Planning timeline

DateStage
1 November 2023Application submitted
10 January 2024Planning permission granted
10 January 2027Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
9.9 MW
Status (REPD)
approved, not built
Record last updated
16 January 2024
Operator or applicant
Biomass Energy Renewables Llp
Planning authority
Stirling
Planning application reference
2023/0372/DET
Address (REPD)
Acharn Forest, Killin, Tayside, lomond
Council area (by location)
Stirling
Time to decision
10 weeks
Name in REPD
Acharn Forest - Battery Storage
REPD reference
15321

Who decides

ApplicationsStirlingUK
Decided applications (solar, wind, battery)2310,236
Refused7 (30%)19%
Solar refused0 of 712%
Onshore wind refused6 of 1145%
Battery storage refused1 of 516%
Median time from submission to decision30.1 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Killin Switching Station, Boreland - Boreland Energy Storage Parkbattery storage43approved, not built3.4
Tir Artairbattery storage49.9approved, not built4.9
Glentarken Wind Farmwind farm104application submitted10.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.4476, -4.3445).