Energy Projects Near You

Killin Switching Station, Boreland - Boreland Energy Storage Park (43 MW)

Killin Switching Station, Boreland - Boreland Energy Storage Park is a 43 MW battery storage project in Stirling, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 8 September 2025, not yet built; the record was last updated on 7 October 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

43 MWbattery storage
approved, not builtstatus in REPD
7 October 2025record last updated
Stirlingcouncil area

Planning timeline

DateStage
30 April 2025Application submitted
8 September 2025Planning permission granted
8 September 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
43 MW
Status (REPD)
approved, not built
Record last updated
7 October 2025
Operator or applicant
Boreland Energy Limited
Planning authority
Stirling
Planning application reference
25/00246/FUL
Address (REPD)
E/O Killin Switching Station, Boreland, Glen Lochay, Killin
Council area (by location)
Stirling
Time to decision
19 weeks
REPD reference
12598

Who decides

ApplicationsStirlingUK
Decided applications (solar, wind, battery)2310,236
Refused7 (30%)19%
Solar refused0 of 712%
Onshore wind refused6 of 1145%
Battery storage refused1 of 516%
Median time from submission to decision30.1 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Tir Artairbattery storage49.9approved, not built2.1
Acharn Forestbattery storage9.9approved, not built3.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.4772, -4.3314).