Energy Projects Near You

Aldeby Landfill Site Solar Park (7 MW)

Aldeby Landfill Site Solar Park is a 7 MW solar farm project in South Norfolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 8 April 2022, not yet built; the record was last updated on 14 March 2022. REPD also records that the planning permission expired on 8 April 2025, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7 MWsolar farm
approved, not builtmay be out of datestatus in REPD
14 March 2022record last updated
South Norfolkcouncil area

REPD also records that the planning permission expired on 8 April 2025, so the project may not go ahead in this form.

Planning timeline

DateStage
7 July 2021Application submitted
8 April 2022Planning permission granted
8 April 2025Permission expired

Project details

Technology
solar farm
Capacity
7 MW
Status (REPD)
approved, not built
Record last updated
14 March 2022
Operator or applicant
Infinis Solar Developments Limited
Planning authority
South Norfolk
Planning application reference
FUL/2021/0015
Site area
11.0 ha
Address (REPD)
Aldeby Landfill Site, Beccles
Council area (by location)
South Norfolk
Time to decision
39 weeks
REPD reference
8365

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsSouth NorfolkUK
Decided applications (solar, wind, battery)5010,236
Refused8 (16%)19%
Solar refused1 of 3012%
Onshore wind refused7 of 745%
Battery storage refused0 of 1316%
Median time from submission to decision20.6 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Ellough Airfield (Ellough 2 extension)solar farm10operational4.9
Playters Solar Farmsolar farm8.6operational5.3
Ellough Airfield (Resubmission)solar farm13.2operational5.4
Devonshire Farmwind farm9refused6.5
Ashby Dell, Border Lane Solar Farmsolar farm30application submitted7.7
Granary farmwind farm9refused7.8
Redisham Hall Farm, School Roadsolar farm42application submitted9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.4813, 1.6254).