Ellough Airfield (Ellough 2 extension) (10 MW solar farm)

Ellough Airfield (Ellough 2 extension) is a 10 MW solar farm project in East Suffolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2016; the record was last updated on 26 April 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWsolar farm
operationalstatus in REPD
26 April 2016record last updated
East Suffolkcouncil area

Planning timeline

DateStage
25 September 2012Application submitted
12 February 2013Refused by the planning authority
16 October 2013Planning permission granted
16 October 2013Appeal allowed
17 October 2013Secretary of State intervened
12 March 2015Secretary of State granted
1 May 2015Construction started
31 March 2016Operational

Project details

Technology
solar farm
Capacity
10 MW
Status (REPD)
operational
Record last updated
26 April 2016
Operator or applicant
Lark Energy
Planning authority
East Suffolk
Planning application reference
DC/12/1113/FUL
Appeal reference
APP/006/2013
Site area
48.0 ha
Address (REPD)
Land At Former Ellough Airfield,
Council area (by location)
East Suffolk
Time to decision
55 weeks
REPD reference
1753

Who decides

ApplicationsEast SuffolkUK
Decided applications (solar, wind, battery)5510,236
Refused10 (18%)19%
Solar refused3 of 3812%
Onshore wind refused5 of 845%
Battery storage refused2 of 916%
Median time from submission to decision15.0 weeks17.0 weeks
Appeals lodged / allowed0 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Ellough Airfield (Resubmission)solar farm13.2operational0.5
Playters Solar Farmsolar farm8.6operational1.3
Devonshire Farmwind farm9refused3.9
Granary farmwind farm9refused4.7
Aldeby Landfill Site Solar Parksolar farm7approved, not built4.9
Redisham Hall Farm, School Roadsolar farm42application submitted5.8
Bernard Matthews Wind Farmwind farm11.5application withdrawn9.5
Upper Holton Wind Farmwind farm11.5operational9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.4388, 1.6059).