Energy Projects Near You

AUCHLEAND FARM Wind Farm (23.8 MW)

AUCHLEAND FARM Wind Farm is a 23.8 MW wind farm project in Dumfries and Galloway, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 5 July 2016; the record was last updated on 3 August 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

23.8 MWwind farm
application withdrawnstatus in REPD
3 August 2016record last updated
Dumfries and Gallowaycouncil area

Planning timeline

DateStage
9 December 2013Application submitted
5 July 2016Application withdrawn

Project details

Technology
wind farm
Capacity
23.8 MW
Status (REPD)
application withdrawn
Record last updated
3 August 2016
Operator or applicant
Community Windpower
Planning authority
Dumfries and Galloway
Planning application reference
13/P/1/0366
Turbines
7
Address (REPD)
Auchleand Farm, Wigtown
Council area (by location)
Dumfries and Galloway
REPD reference
4461

Who decides

ApplicationsDumfries and GallowayUK
Decided applications (solar, wind, battery)10610,236
Refused40 (38%)19%
Solar refused1 of 1812%
Onshore wind refused33 of 7245%
Battery storage refused6 of 1616%
Median time from submission to decision60.9 weeks17.0 weeks
Appeals lodged / allowed19 / 17—

Other large projects within 10 km

ProjectTypeMWStatuskm
Balmurrie Fell Wind Farmwind farm9.1operational3.0
Shennanton Wind Farmwind farm30application submitted8.5
Challoch, Barnkirk Road Solar Array & Battery Energy Storagebattery storage6application submitted9.0
Challoch, Barnkirk Road Solar Array & Battery Energy Storagesolar farm20application submitted9.0
Shennanton Wind Farmwind farm30refused on appeal9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.8956, -4.4936).