Balmurrie Fell Wind Farm (9.1 MW)

Balmurrie Fell Wind Farm is a 9.1 MW wind farm project in Dumfries and Galloway, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 September 2012; the record was last updated on 4 June 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9.1 MWwind farm
operationalstatus in REPD
4 June 2020record last updated
Dumfries and Gallowaycouncil area

Planning timeline

DateStage
30 June 2009Application submitted
25 November 2011Planning permission granted
1 March 2012Construction started
1 September 2012Operational

Project details

Technology
wind farm
Capacity
9.1 MW
Status (REPD)
operational
Record last updated
4 June 2020
Operator or applicant
Scottish Southern Energy
Planning authority
Dumfries and Galloway
Planning application reference
09/P/1/0224
Turbines
7
Address (REPD)
Balmurrie Fell, Newton Stewart, Dunfries & Galloway. DG8
Council area (by location)
Dumfries and Galloway
Time to decision
125 weeks
REPD reference
4445

Who decides

ApplicationsDumfries and GallowayUK
Decided applications (solar, wind, battery)10610,236
Refused40 (38%)19%
Solar refused1 of 1812%
Onshore wind refused33 of 7245%
Battery storage refused6 of 1616%
Median time from submission to decision60.9 weeks17.0 weeks
Appeals lodged / allowed19 / 17—

Other large projects within 10 km

ProjectTypeMWStatuskm
AUCHLEAND FARM Wind Farmwind farm23.8application withdrawn3.0
Shennanton Wind Farmwind farm30application submitted9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.8725, -4.5165).