Ballyboley Solar (Carrowdore) (6 MW)

Ballyboley Solar (Carrowdore) is a 6 MW solar farm project in Ards and North Down, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 28 February 2017; the record was last updated on 18 April 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6 MWsolar farm
operationalstatus in REPD
18 April 2017record last updated
Ards and North Downcouncil area

Planning timeline

DateStage
3 October 2014Application submitted
3 June 2015Planning permission granted
1 October 2016Construction started
28 February 2017Operational

Project details

Technology
solar farm
Capacity
6 MW
Status (REPD)
operational
Record last updated
18 April 2017
Operator or applicant
Island Green Power
Planning authority
Ards and North Down
Planning application reference
X/2014/0538/F
Address (REPD)
Lands 88m West of 2a Ballyblack Road East, Carrowdore, Newtownards
Council area (by location)
Ards and North Down
Time to decision
35 weeks
REPD reference
4724

Who decides

Ards and North Down has 3 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.5716, -5.5692).