Energy Projects Near You

Renewable energy projects in Northern Ireland

Northern Ireland has 476 solar, onshore wind or battery projects of 150 kW or more in the Renewable Energy Planning Database (July 2026 extract): 100 awaiting a decision, 168 approved but not running and 105 operational. 16% of 334 decided applications were refused.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

476projects
100awaiting a decision
168approved, not running
16%of decisions refused

Councils in Northern Ireland

CouncilProjectsPendingApprovedOperationalRefused
Antrim and Newtownabbey422171420%
Ards and North Down9421—
Armagh City, Banbridge and Craigavon331313212%
Belfast7130—
Causeway Coast and Glens6813202213%
Derry City and Strabane8222211620%
Fermanagh and Omagh10316372816%
Lisburn and Castlereagh12155—
Mid Ulster641427916%
Mid and East Antrim421116717%
Newry, Mourne and Down14371—

Refused: share of decided applications refused by the council (shown from 10 decisions).

Largest applications awaiting a decision

ProjectTypeMWSubmittedRecord updatedCouncil
Maydown Roadbattery storagebattery storage140Nov 2024Jan 2025Derry City and Strabane
Energy Storage System Installation in Rasharkinbattery storagebattery storage100Feb 2025Apr 2025Causeway Coast and Glens
Skreen Roadbattery storagebattery storage100Dec 2024Feb 2025Fermanagh and Omagh
Mullaghmeash Road & Feenybattery storagebattery storage100Feb 2025Apr 2025Derry City and Strabane
Power Generation Development in Islandmageebattery storagebattery storage100Jun 2023 may be out of dateDec 2025Mid and East Antrim
Battery Energy Storage System Development in Drumquinbattery storagebattery storage87.8Nov 2024Jan 2025Fermanagh and Omagh
Power Generation in Development in Claudybattery storagebattery storage75Dec 2022 may be out of dateDec 2025Derry City and Strabane
Townland of Tattymoyle Middle, Ecclesville Road Wind Farmwind farmwind farm72May 2026—Fermanagh and Omagh
Unshinagh Wind Farm Development in Carnloughwind farmwind farm58.8Dec 2021 may be out of dateJul 2022Mid and East Antrim
Carnbuck Wind Farmwind farmwind farm50.4Feb 2023 may be out of dateJun 2023Mid and East Antrim
Kells Solar Farmsolar farmsolar farm50Jun 2015 may be out of dateFeb 2016Mid and East Antrim
Trench Road, Killymallaght Substationbattery storagebattery storage50Sep 2024Dec 2024Derry City and Strabane
Colinglen Road Batterybattery storagebattery storage49.9Jul 2020 may be out of dateAug 2022Lisburn and Castlereagh
Gruggandoo Wind Farmwind farmwind farm39.6Mar 2015 may be out of dateMay 2015Newry, Mourne and Down
Brishey Wind Farmwind farmwind farm28.8Jan 2023 may be out of dateApr 2023Causeway Coast and Glens
Cullion wind farmwind farmwind farm25Jul 2019 may be out of dateSep 2019Mid Ulster
Carnalbanagh Windfarmwind farmwind farm21Jun 2017 may be out of dateAug 2017Mid and East Antrim
Dunbeg South Wind Farm - Extensionwind farmwind farm16.8Nov 2024Jun 2026Causeway Coast and Glens
Carrickmannon Road, Ballygowanwind turbinewind turbine8.8May 2024 may be out of dateJul 2024Ards and North Down
62 Muldonagh Road, Claudywind turbinewind turbine8.8Jun 2023 may be out of dateNov 2023Causeway Coast and Glens