Energy Projects Near You

Renewable energy projects in Mid and East Antrim

42 solar, wind or battery projects of 150 kW or more are located in Mid and East Antrim (REPD, July 2026 extract): 11 pending, 16 approved but not running, 7 operational and 4 refused. The council refused 5 of 30 decided applications (17%; UK 19%), with a median 45 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

42projects in the council area
11awaiting a decision
16approved, not running
17%of decisions refused

How Mid and East Antrim decides

ApplicationsMid and East AntrimUK
Decided applications (solar, wind, battery)3010,236
Refused5 (17%)19%
Solar refused0 of 612%
Onshore wind refused5 of 2245%
Battery storage refused0 of 216%
Median time from submission to decision45.2 weeks17.0 weeks
Appeals lodged / allowed5 / 1—

Projects in Mid and East Antrim

Projects of 1 MW and more (24)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Power Generation Development in Islandmageebattery storagebattery storage100application submitted may be out of dateupdated Dec 2025Jun 2023—Dec 2025
Quarterland Road, Islandmageebattery storagebattery storage75approved, not builtupdated Jan 2024Mar 2023granted Jan 2024Jan 2024
Unshinagh Wind Farm Development in Carnloughwind farmwind farm58.8application submitted may be out of dateupdated Jul 2022Dec 2021—Jul 2022
Douglas Topwind farmwind farm51application withdrawnupdated Sep 2012Apr 2011—Sep 2012
Carnbuck Wind Farmwind farmwind farm50.4application submitted may be out of dateupdated Jun 2023Feb 2023—Jun 2023
Kells Solar Farmsolar farmsolar farm50application submitted may be out of dateupdated Feb 2016Jun 2015—Feb 2016
Elginny Hillwind farmwind farm22operationalupdated Oct 2018Mar 2011granted Nov 2014Oct 2018
Land at Dobbs Estatesolar farmsolar farm21.8abandonedupdated Apr 2018Mar 2015granted Mar 2016Apr 2018
Rathsherrywind farmwind farm21operationalupdated Feb 2018Apr 2011granted Mar 2015Feb 2018
Carnalbanagh Windfarmwind farmwind farm21application submitted may be out of dateupdated Aug 2017Jun 2017—Aug 2017
Ballykeel Wind Farmwind farmwind farm16.1approved, not built may be out of dateupdated Sep 2018Dec 2013granted Dec 2016Sep 2018
Feystown Wind Farmwind farmwind farm13.8refused on appealupdated Aug 2016May 2013refused Dec 2014Aug 2016
Cloghinarneywind farmwind farm13.8refused on appealupdated May 2016Apr 2011refused Jul 2014May 2016
Ballygarvey Roadsolar farmsolar farm13operationalupdated Jun 2018Dec 2015granted Sep 2016Jun 2018
Mullaghsandall Road wind farmwind farmwind farm10refused on appealupdated May 2016Apr 2013refused Jul 2014May 2016
AES Kilroot Station Battery Storage Arraybattery storagebattery storage10operationalupdated Dec 2018——Dec 2018
Wolf Bog Wind Farmwind farmwind farm8.8operationalupdated Feb 2010May 2004granted Nov 2005Feb 2010
Red Braesolar farmsolar farm5permission expiredupdated Jun 2019Mar 2015granted Oct 2015Jun 2019
Ballymena Wind Park Limitedwind farmwind farm4.7operationalupdated Aug 2013Jul 2009granted Apr 2010Aug 2013
The Michelin Tyre Factory - Ballymenawind farmwind farm4.6operationalupdated Apr 2013Jul 2009granted Feb 2010Apr 2013
Solar Farm Development in Ballymenasolar farmsolar farm3.5approved, not builtupdated May 2025Dec 2024granted Apr 2025May 2025
Solar PV Development in Ballymenasolar farmsolar farm2.5approved, not builtupdated Sep 2024Apr 2024granted Aug 2024Sep 2024
Solar PV Energy Development in Ballymenasolar farmsolar farm2approved, not builtupdated Sep 2024Apr 2024granted Aug 2024Sep 2024
Battery Energy Storage System in Broughshanebattery storagebattery storage1approved, not builtupdated Mar 2024Oct 2023granted Feb 2024Mar 2024
Smaller schemes under 1 MW, mostly rooftop solar (18)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
93 Caddy Roadwind turbinewind turbine0.8approved, not builtupdated Dec 2023Jan 2023granted Dec 2023Dec 2023
402 metres NE of 45 Dickeystown Roadwind turbinewind turbine0.3approved, not built may be out of dateupdated Jan 2020Aug 2017granted Mar 2019Jan 2020
Larne Roadwind turbinewind turbine0.3approved, not built may be out of dateupdated Feb 2021Nov 2019granted Jan 2021Feb 2021
Woodside Roadwind turbinewind turbine0.3approved, not built may be out of dateupdated Feb 2020Dec 2019granted Oct 2020Feb 2020
Omerbane Road, Cloughmills Replacementwind turbinewind turbine0.2approved, not builtupdated Sep 2021Aug 2021granted Mar 2022Sep 2021
85 Deerfin Road, Ballymenawind turbinewind turbine0.2refusedupdated Sep 2024Apr 2023refused Sep 2024Sep 2024
Carmagrim Roadwind turbinewind turbine0.2approved, not built may be out of dateupdated Jun 2020Jan 2020granted Apr 2021Jun 2020
Replacement Wind Turbinewind turbinewind turbine0.1approved, not built may be out of dateupdated Jan 2022Jan 2021granted Jul 2021Jan 2022
Garvaghy Roadwind turbinewind turbine—application submitted may be out of dateupdated Dec 2022Oct 2020—Dec 2022
Loughmourne Roadwind turbinewind turbine—application submitted may be out of dateupdated Jun 2022Dec 2020—Jun 2022
58 Tullykiagh Roadwind turbinewind turbine—approved, not builtupdated Nov 2023Jan 2023granted Jul 2023Nov 2023
Carnbuck Wind Farmbattery storagebattery storage—application submitted may be out of dateupdated Aug 2023Feb 2023—Aug 2023
Wind Turbine Development in Broughshanewind turbinewind turbine—approved, not builtupdated Mar 2024Oct 2023granted Feb 2024Mar 2024
Omerbane Road, Cloughmillswind turbinewind turbine—approved, not builtupdated Jan 2025May 2024granted Jan 2025Jan 2025
Solar PV Farm Development in Carrickfergusrooftop solarrooftop solar—application submittedupdated Nov 2024Sep 2024—Nov 2024
Solar Farm Development in Ballymenasolar farmsolar farm—application submittedupdated Nov 2024Sep 2024—Nov 2024
Wind Turbine Development in Ballyclarewind turbinewind turbine—application withdrawnupdated Nov 2025Oct 2024—Nov 2025
Wind Turbine Development in Ballymenawind turbinewind turbine—application submittedupdated May 2025Mar 2025—May 2025

Postcode districts in Mid and East Antrim

DistrictProjects within 10 kmPendingApprovedOperational
BT389312
BT406230
BT4218494
BT4313345

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Mid and East Antrim by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.