Energy Projects Near You

Solar, wind and battery projects near Carrickfergus (BT38)

9 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of BT38 (Mid and East Antrim): 3 are waiting for a planning decision, 1 approved but not yet running, 2 operational. The largest live scheme is Power Generation Development in Islandmagee (100 MW battery storage, application submitted on 27 June 2023, no decision recorded; REPD status may be out of date), 9.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9projects within 10 km
3awaiting a decision
1approved, not running
2operational

Projects within 10 km of BT38

Projects of 1 MW and more (6)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
AES Kilroot Station Battery Storage Arraybattery storagebattery storage10operationalupdated Dec 2018——Dec 2018Mid and East Antrim2.3
Red Braesolar farmsolar farm5permission expiredupdated Jun 2019Mar 2015granted Oct 2015Jun 2019Mid and East Antrim2.3
Land at Dobbs Estatesolar farmsolar farm21.8abandonedupdated Apr 2018Mar 2015granted Mar 2016Apr 2018Mid and East Antrim2.7
Carn Hillwind farmwind farm13.8operationalupdated Jan 2017Feb 2006granted Feb 2010Jan 2017Antrim and Newtownabbey7.1
Doagh Road Solar Farmsolar farmsolar farm5appeal withdrawnupdated Jun 2016Mar 2015refused Oct 2015Jun 2016Antrim and Newtownabbey9.6
Power Generation Development in Islandmageebattery storagebattery storage100application submitted may be out of dateupdated Dec 2025Jun 2023—Dec 2025Mid and East Antrim9.9
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Solar PV Farm Development in Carrickfergusrooftop solarrooftop solar—application submittedupdated Nov 2024Sep 2024—Nov 2024Mid and East Antrim3.4
Loughmourne Roadwind turbinewind turbine—application submitted may be out of dateupdated Jun 2022Dec 2020—Jun 2022Mid and East Antrim4.8
Larne Roadwind turbinewind turbine0.3approved, not built may be out of dateupdated Feb 2021Nov 2019granted Jan 2021Feb 2021Mid and East Antrim7.6

Distance from the average position of the BT38 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm300000
Rooftop solar110000
Wind farm100100
Wind turbine211000.3
Battery storage21010100

MW in pipeline: pending, approved and under-construction capacity.

How Mid and East Antrim decides solar, wind and battery applications

ApplicationsMid and East AntrimUK
Decided applications (solar, wind, battery)3010,236
Refused5 (17%)19%
Solar refused0 of 612%
Onshore wind refused5 of 2245%
Battery storage refused0 of 216%
Median time from submission to decision45.2 weeks17.0 weeks
Appeals lodged / allowed5 / 1—

All projects in Mid and East Antrim

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near BT38, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.