AES Kilroot Station Battery Storage Array (10 MW)

AES Kilroot Station Battery Storage Array is a 10 MW battery storage project in Mid and East Antrim, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 18 January 2016; the record was last updated on 12 December 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWbattery storage
operationalstatus in REPD
12 December 2018record last updated
Mid and East Antrimcouncil area

Planning timeline

DateStage
18 November 2015Construction started
18 January 2016Operational

Project details

Technology
battery storage (co-located with fossil fuel plant)
Capacity
10 MW
Status (REPD)
operational
Record last updated
12 December 2018
Operator or applicant
AES Kilroot Power (AES KPL)
Planning authority
Mid and East Antrim
Planning application reference
not recorded
Address (REPD)
Carrickfergus
Council area (by location)
Mid and East Antrim
REPD reference
6845

Who decides

ApplicationsMid and East AntrimUK
Decided applications (solar, wind, battery)3010,236
Refused5 (17%)19%
Solar refused0 of 612%
Onshore wind refused5 of 2245%
Battery storage refused0 of 216%
Median time from submission to decision45.2 weeks17.0 weeks
Appeals lodged / allowed5 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land at Dobbs Estatesolar farm21.8abandoned2.2
Red Braesolar farm5permission expired3.8
Carn Hillwind farm13.8operational9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.7244, -5.7672).