Energy Projects Near You

Land at Dobbs Estate (21.8 MW solar farm)

Land at Dobbs Estate is a 21.8 MW solar farm project in Mid and East Antrim, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 30 April 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

21.8 MWsolar farm
abandonedstatus in REPD
30 April 2018record last updated
Mid and East Antrimcouncil area

Planning timeline

DateStage
25 March 2015Application submitted
14 March 2016Planning permission granted
13 March 2021Permission expired

Project details

Technology
solar farm
Capacity
21.8 MW
Status (REPD)
abandoned
Record last updated
30 April 2018
Operator or applicant
Lightsource Renewable Energy
Planning authority
Mid and East Antrim
Planning application reference
V/2015/0038/F
Address (REPD)
Land at Dobbs Estate, Tongue Loanen Road, Carrickfergus
Council area (by location)
Mid and East Antrim
Time to decision
51 weeks
REPD reference
5184

Who decides

ApplicationsMid and East AntrimUK
Decided applications (solar, wind, battery)3010,236
Refused5 (17%)19%
Solar refused0 of 612%
Onshore wind refused5 of 2245%
Battery storage refused0 of 216%
Median time from submission to decision45.2 weeks17.0 weeks
Appeals lodged / allowed5 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
AES Kilroot Station Battery Storage Arraybattery storage10operational2.2
Red Braesolar farm5permission expired2.5
Power Generation Development in Islandmageebattery storage100application submitted8.1
Carn Hillwind farm13.8operational9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.7443, -5.7687).