Carn Hill (13.8 MW wind farm)

Carn Hill is a 13.8 MW wind farm project in Antrim and Newtownabbey, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 8 May 2013; the record was last updated on 3 January 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13.8 MWwind farm
operationalstatus in REPD
3 January 2017record last updated
Antrim and Newtownabbeycouncil area

Planning timeline

DateStage
17 February 2006Application submitted
12 February 2010Planning permission granted
1 May 2012Construction started
8 May 2013Operational

Project details

Technology
wind farm
Capacity
13.8 MW
Status (REPD)
operational
Record last updated
3 January 2017
Operator or applicant
Gaelectric Developments/ CGN Europe Energy
Planning authority
Antrim and Newtownabbey
Planning application reference
U/2006/0054/F
Turbines
6
Address (REPD)
Lands north of Slievetrue Road, Carn Hill/Rea Hill, Newtownabbey, Co Antrim
Council area (by location)
Antrim and Newtownabbey
Time to decision
208 weeks
REPD reference
3934

Who decides

ApplicationsAntrim and NewtownabbeyUK
Decided applications (solar, wind, battery)4010,236
Refused8 (20%)19%
Solar refused4 of 1412%
Onshore wind refused3 of 1945%
Battery storage refused1 of 716%
Median time from submission to decision48.1 weeks17.0 weeks
Appeals lodged / allowed7 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: Antrim and Newtownabbey, South Antrim.

Other large projects within 10 km

ProjectTypeMWStatuskm
Doagh Road Solar Farmsolar farm5appeal withdrawn4.1
Sealstown Road Solar Farmsolar farm6.7abandoned5.0
Red Braesolar farm5permission expired7.1
Gibson Farmsolar farm6.4operational9.1
Land at Dobbs Estatesolar farm21.8abandoned9.3
AES Kilroot Station Battery Storage Arraybattery storage10operational9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.7313, -5.9118).