Energy Projects Near You

Gibson Farm (6.4 MW solar farm)

Gibson Farm is a 6.4 MW solar farm project in Antrim and Newtownabbey, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 28 February 2018; the record was last updated on 4 September 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.4 MWsolar farm
operationalstatus in REPD
4 September 2018record last updated
Antrim and Newtownabbeycouncil area

Planning timeline

DateStage
4 December 2015Application submitted
26 July 2016Planning permission granted
11 December 2017Construction started
28 February 2018Operational

Project details

Technology
solar farm
Capacity
6.4 MW
Status (REPD)
operational
Record last updated
4 September 2018
Operator or applicant
Lightsource Renewable Energy
Planning authority
Antrim and Newtownabbey
Planning application reference
LA03/2015/0655/F
Site area
15.0 ha
Address (REPD)
Land at Gibson Farm, Sealstown Road, Newtownabbey
Council area (by location)
Antrim and Newtownabbey
Time to decision
34 weeks
REPD reference
5977

Who decides

ApplicationsAntrim and NewtownabbeyUK
Decided applications (solar, wind, battery)4010,236
Refused8 (20%)19%
Solar refused4 of 1412%
Onshore wind refused3 of 1945%
Battery storage refused1 of 716%
Median time from submission to decision48.1 weeks17.0 weeks
Appeals lodged / allowed7 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: Antrim and Newtownabbey, South Antrim.

Other large projects within 10 km

ProjectTypeMWStatuskm
Ballyutoag Wind Farmwind farm11.5approved, not built3.3
Sealstown Road Solar Farmsolar farm6.7abandoned4.4
Doagh Road Solar Farmsolar farm5appeal withdrawn5.4
Lands West of Belfast Roadsolar farm10operational7.7
South of Ballyscultysolar farm6.2refused on appeal8.1
Carn Hillwind farm13.8operational9.1
Elliot's Hill Wind Farmwind farm5operational9.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.6754, -6.016).