South of Ballysculty (6.2 MW solar farm)

South of Ballysculty is a 6.2 MW solar farm project in Antrim and Newtownabbey, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 31 March 2016; the record was last updated on 5 April 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.2 MWsolar farm
refused on appealstatus in REPD
5 April 2016record last updated
Antrim and Newtownabbeycouncil area

Planning timeline

DateStage
6 November 2014Application submitted
27 August 2015Refused by the planning authority
29 September 2015Appeal lodged
31 March 2016Appeal refused

Project details

Technology
solar farm
Capacity
6.2 MW
Status (REPD)
refused on appeal
Record last updated
5 April 2016
Operator or applicant
Lightsource Renewable Energy
Planning authority
Antrim and Newtownabbey
Planning application reference
T/2014/0460/F
Appeal reference
2015/A0135
Address (REPD)
Land 130m South of no 28 Ballysculty Road, Muckamore
Council area (by location)
Antrim and Newtownabbey
Time to decision
42 weeks
REPD reference
5614

Who decides

ApplicationsAntrim and NewtownabbeyUK
Decided applications (solar, wind, battery)4010,236
Refused8 (20%)19%
Solar refused4 of 1412%
Onshore wind refused3 of 1945%
Battery storage refused1 of 716%
Median time from submission to decision48.1 weeks17.0 weeks
Appeals lodged / allowed7 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: Antrim and Newtownabbey, South Antrim.

Other large projects within 10 km

ProjectTypeMWStatuskm
Lands West of Belfast Roadsolar farm10operational4.3
Battery Energy Storage System Facility in Antrimbattery storage50approved, not built5.5
South Antrim Solar Park - Phase 1solar farm6.5operational6.5
South Antrim Solar Park - Phase 2solar farm39.5approved, not built6.5
Knockcairn Roadsolar farm6.5operational7.1
Elliot's Hill Wind Farmwind farm5operational7.7
Moira Roadsolar farm6.5operational7.7
Ballyutoag Wind Farmwind farm11.5approved, not built7.9
Gibson Farmsolar farm6.4operational8.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.6711, -6.1414).