Energy Projects Near You

Ballyutoag Wind Farm (11.5 MW)

Ballyutoag Wind Farm is an 11.5 MW wind farm project in Antrim and Newtownabbey, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 23 December 2015, not yet built; the record was last updated on 23 September 2020. REPD also records that the planning permission expired on 21 December 2020, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11.5 MWwind farm
approved, not builtmay be out of datestatus in REPD
23 September 2020record last updated
Antrim and Newtownabbeycouncil area

REPD also records that the planning permission expired on 21 December 2020, so the project may not go ahead in this form.

Planning timeline

DateStage
8 December 2014Application submitted
23 December 2015Planning permission granted
21 December 2020Permission expired

Project details

Technology
wind farm
Capacity
11.5 MW
Status (REPD)
approved, not built
Record last updated
23 September 2020
Operator or applicant
BSI Wind (formerly TCI Renewables)
Planning authority
Antrim and Newtownabbey
Planning application reference
T/2014/0478/F
Turbines
5
Turbine height
93 m
Address (REPD)
Land approximately 1km north of No. 71 Ballyutoag Road, Belfast, Co. Antrim
Council area (by location)
Antrim and Newtownabbey
Time to decision
54 weeks
REPD reference
4902

Who decides

ApplicationsAntrim and NewtownabbeyUK
Decided applications (solar, wind, battery)4010,236
Refused8 (20%)19%
Solar refused4 of 1412%
Onshore wind refused3 of 1945%
Battery storage refused1 of 716%
Median time from submission to decision48.1 weeks17.0 weeks
Appeals lodged / allowed7 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: Antrim and Newtownabbey, South Antrim.

Other large projects within 10 km

ProjectTypeMWStatuskm
Gibson Farmsolar farm6.4operational3.3
Lands West of Belfast Roadsolar farm10operational5.8
Sealstown Road Solar Farmsolar farm6.7abandoned6.9
Colinglen Road Batterybattery storage49.9application submitted7.5
Doagh Road Solar Farmsolar farm5appeal withdrawn7.9
South of Ballyscultysolar farm6.2refused on appeal7.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.6466, -6.0259).