Sealstown Road Solar Farm (6.7 MW)

Sealstown Road Solar Farm is a 6.7 MW solar farm project in Antrim and Newtownabbey, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 30 April 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.7 MWsolar farm
abandonedstatus in REPD
30 April 2018record last updated
Antrim and Newtownabbeycouncil area

Planning timeline

DateStage
25 June 2015Application submitted
17 November 2015Planning permission granted
16 November 2020Permission expired

Project details

Technology
solar farm
Capacity
6.7 MW
Status (REPD)
abandoned
Record last updated
30 April 2018
Operator or applicant
Lightsource Renewable Energy
Planning authority
Antrim and Newtownabbey
Planning application reference
LA03/2015/0250/F
Address (REPD)
Sealstown Road, Newtownabbey, Co Antrim
Council area (by location)
Antrim and Newtownabbey
Time to decision
21 weeks
REPD reference
5463

Who decides

ApplicationsAntrim and NewtownabbeyUK
Decided applications (solar, wind, battery)4010,236
Refused8 (20%)19%
Solar refused4 of 1412%
Onshore wind refused3 of 1945%
Battery storage refused1 of 716%
Median time from submission to decision48.1 weeks17.0 weeks
Appeals lodged / allowed7 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: Antrim and Newtownabbey, South Antrim.

Other large projects within 10 km

ProjectTypeMWStatuskm
Doagh Road Solar Farmsolar farm5appeal withdrawn1.0
Gibson Farmsolar farm6.4operational4.4
Carn Hillwind farm13.8operational5.0
Ballyutoag Wind Farmwind farm11.5approved, not built6.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.694, -5.9556).