Energy Projects Near You

Solar, wind and battery projects near Newtownabbey (BT36)

19 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of BT36 (Antrim and Newtownabbey): 2 are waiting for a planning decision, 6 approved but not yet running, 4 operational. The largest live scheme is Ballyutoag Wind Farm (11.5 MW wind farm, approved on 23 December 2015, not yet built; REPD status may be out of date), 5.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

19projects within 10 km
2awaiting a decision
6approved, not running
4operational

Projects within 10 km of BT36

Projects of 1 MW and more (12)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Bombardier Factoryrooftop solarrooftop solar3.8operationalupdated Jun 2015Nov 2013granted Feb 2014Jun 2015Antrim and Newtownabbey1.2
Sealstown Road Solar Farmsolar farmsolar farm6.7abandonedupdated Apr 2018Jun 2015granted Nov 2015Apr 2018Antrim and Newtownabbey1.9
Doagh Road Solar Farmsolar farmsolar farm5appeal withdrawnupdated Jun 2016Mar 2015refused Oct 2015Jun 2016Antrim and Newtownabbey2.6
Gibson Farmsolar farmsolar farm6.4operationalupdated Sep 2018Dec 2015granted Jul 2016Sep 2018Antrim and Newtownabbey3.8
Development SE of Flush Roadwind turbinewind turbine2permission expiredupdated Aug 2020Jan 2015granted Nov 2015Aug 2020Belfast4.2
Wind Turbine 1wind turbinewind turbine2.3operationalupdated Aug 2012Jun 2009granted Feb 2010Aug 2012Antrim and Newtownabbey4.2
320mts South East of 43 Flush Roadwind turbinewind turbine2permission expiredupdated Aug 2020Nov 2014granted Nov 2015Aug 2020Belfast4.7
Boghill Roadwind turbinewind turbine2application withdrawnupdated Dec 2019Apr 2019—Dec 2019Antrim and Newtownabbey4.9
Lands at Ballyutoag Roadwind turbinewind turbine2.3approved, not built may be out of dateupdated Apr 2020Jun 2016granted Aug 2018Apr 2020Belfast5.0
Ballyutoag Wind Farmwind farmwind farm11.5approved, not built may be out of dateupdated Sep 2020Dec 2014granted Dec 2015Sep 2020Antrim and Newtownabbey5.6
Carn Hillwind farmwind farm13.8operationalupdated Jan 2017Feb 2006granted Feb 2010Jan 2017Antrim and Newtownabbey6.7
Solar PV Energy Alterations in Belfastsolar farmsolar farm2application submitted may be out of dateupdated Jun 2024Apr 2024—Jun 2024Belfast9.1
Smaller schemes under 1 MW, mostly rooftop solar (7)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Boghill Road Wind Turbinewind turbinewind turbine—approved, not built may be out of dateupdated Nov 2022Feb 2021granted Oct 2022Nov 2022Antrim and Newtownabbey2.6
Upper Hightown Roadwind turbinewind turbine0.2refusedupdated Mar 2023Mar 2020refused Jan 2023Mar 2023Belfast3.6
Aughnabrack Road Replacement Turbinewind turbinewind turbine—approved, not builtupdated Jul 2022Feb 2021granted Jul 2022Jul 2022Antrim and Newtownabbey5.3
Ballyutoag Roadwind turbinewind turbine0.2approved, not builtupdated Jan 2021Dec 2020granted Dec 2021Jan 2021Belfast5.4
Power Generation Development in Templepatrickwind turbinewind turbine0.2refusedupdated May 2024Feb 2023refused Apr 2024May 2024Antrim and Newtownabbey7.2
Budore Road, Ligonielwind farmwind farm—application submitted may be out of dateupdated May 2024Apr 2024—May 2024Antrim and Newtownabbey8.5
Laurel Lanewind turbinewind turbine0.5approved, not built may be out of dateupdated Apr 2020May 2019granted Apr 2020Apr 2020Antrim and Newtownabbey9.2

Distance from the average position of the BT36 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm410102
Rooftop solar100100
Wind farm3111011.5
Wind turbine1105123

MW in pipeline: pending, approved and under-construction capacity.

How Antrim and Newtownabbey decides solar, wind and battery applications

ApplicationsAntrim and NewtownabbeyUK
Decided applications (solar, wind, battery)4010,236
Refused8 (20%)19%
Solar refused4 of 1412%
Onshore wind refused3 of 1945%
Battery storage refused1 of 716%
Median time from submission to decision48.1 weeks17.0 weeks
Appeals lodged / allowed7 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: Antrim and Newtownabbey, South Antrim.

All projects in Antrim and Newtownabbey

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near BT36, 6 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.