Energy Projects Near You

Lands West of Belfast Road (10 MW solar farm)

Lands West of Belfast Road is a 10 MW solar farm project in Antrim and Newtownabbey, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 March 2017; the record was last updated on 3 May 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWsolar farm
operationalstatus in REPD
3 May 2017record last updated
Antrim and Newtownabbeycouncil area

Planning timeline

DateStage
29 June 2015Application submitted
23 December 2015Planning permission granted
15 February 2017Construction started
15 March 2017Operational

Project details

Technology
solar farm
Capacity
10 MW
Status (REPD)
operational
Record last updated
3 May 2017
Operator or applicant
Lightsource Renewable Energy
Planning authority
Antrim and Newtownabbey
Planning application reference
LA03/2015/0257/F
Address (REPD)
Lands Approximately 140m West, 66 Belfast Road, Nutts Corner, Crumlin, Co Antrim
Council area (by location)
Antrim and Newtownabbey
Time to decision
25 weeks
REPD reference
5435

Who decides

ApplicationsAntrim and NewtownabbeyUK
Decided applications (solar, wind, battery)4010,236
Refused8 (20%)19%
Solar refused4 of 1412%
Onshore wind refused3 of 1945%
Battery storage refused1 of 716%
Median time from submission to decision48.1 weeks17.0 weeks
Appeals lodged / allowed7 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: Antrim and Newtownabbey, South Antrim.

Other large projects within 10 km

ProjectTypeMWStatuskm
South of Ballyscultysolar farm6.2refused on appeal4.3
Knockcairn Roadsolar farm6.5operational4.5
Moira Roadsolar farm6.5operational5.7
Ballyutoag Wind Farmwind farm11.5approved, not built5.8
Gibson Farmsolar farm6.4operational7.7
Colinglen Road Batterybattery storage49.9application submitted7.9
Battery Energy Storage System Facility in Antrimbattery storage50approved, not built8.8
Hillside Solar Farmsolar farm25.2operational9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.6356, -6.1148).