Energy Projects Near You

Solar, wind and battery projects near Belfast (BT11)

19 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of BT11 (Belfast): 3 are waiting for a planning decision, 9 approved but not yet running, 3 operational. The largest live scheme is Battery Storage System Development in Lisburn (150 MW battery storage, approved on 30 January 2026, not yet built), 9.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

19projects within 10 km
3awaiting a decision
9approved, not running
3operational

Projects within 10 km of BT11

Projects of 1 MW and more (12)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Colinglen Road Batterybattery storagebattery storage49.9application submitted may be out of dateupdated Aug 2022Jul 2020—Aug 2022Lisburn and Castlereagh2.7
Solar PV Energy Alterations in Belfastsolar farmsolar farm2application submitted may be out of dateupdated Jun 2024Apr 2024—Jun 2024Belfast4.9
320mts South East of 43 Flush Roadwind turbinewind turbine2permission expiredupdated Aug 2020Nov 2014granted Nov 2015Aug 2020Belfast7.2
Development SE of Flush Roadwind turbinewind turbine2permission expiredupdated Aug 2020Jan 2015granted Nov 2015Aug 2020Belfast7.4
Lands at Ballyutoag Roadwind turbinewind turbine2.3approved, not built may be out of dateupdated Apr 2020Jun 2016granted Aug 2018Apr 2020Belfast7.5
Ballyutoag Wind Farmwind farmwind farm11.5approved, not built may be out of dateupdated Sep 2020Dec 2014granted Dec 2015Sep 2020Antrim and Newtownabbey8.0
Lisnabreeny Roadbattery storagebattery storage36approved, not built may be out of dateupdated Jun 2020Jun 2019granted Jun 2019Jun 2020Lisburn and Castlereagh8.9
Ballinderry Road Solar Phase 2 (Lisburn)solar farmsolar farm7operationalupdated Apr 2017May 2015granted Oct 2015Apr 2017Lisburn and Castlereagh9.1
Ballinderry Road Solar Phase 1 (Lisburn)solar farmsolar farm13.5operationalupdated Mar 2017Jul 2014granted Nov 2014Mar 2017Lisburn and Castlereagh9.2
Battery Storage System Development in Lisburnbattery storagebattery storage150approved, not builtupdated Feb 2026Apr 2024granted Jan 2026Feb 2026Lisburn and Castlereagh9.3
Boghill Roadwind turbinewind turbine2application withdrawnupdated Dec 2019Apr 2019—Dec 2019Antrim and Newtownabbey9.5
Lands West of Belfast Roadsolar farmsolar farm10operationalupdated May 2017Jun 2015granted Dec 2015May 2017Antrim and Newtownabbey10.0
Smaller schemes under 1 MW, mostly rooftop solar (7)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Power Generation Development in Belfastwind turbinewind turbine0.6approved, not builtupdated Jun 2026Feb 2023granted Jun 2026Jun 2026Belfast2.8
Laurel Lanewind turbinewind turbine0.5approved, not built may be out of dateupdated Apr 2020May 2019granted Apr 2020Apr 2020Antrim and Newtownabbey5.8
Budore Road, Ligonielwind farmwind farm—application submitted may be out of dateupdated May 2024Apr 2024—May 2024Antrim and Newtownabbey6.0
Ballyutoag Roadwind turbinewind turbine0.2approved, not builtupdated Jan 2021Dec 2020granted Dec 2021Jan 2021Belfast6.8
Upper Hightown Roadwind turbinewind turbine0.2refusedupdated Mar 2023Mar 2020refused Jan 2023Mar 2023Belfast7.9
Aughnabrack Road Replacement Turbinewind turbinewind turbine—approved, not builtupdated Jul 2022Feb 2021granted Jul 2022Jul 2022Antrim and Newtownabbey9.2
Boghill Road Wind Turbinewind turbinewind turbine—approved, not built may be out of dateupdated Nov 2022Feb 2021granted Oct 2022Nov 2022Antrim and Newtownabbey9.6

Distance from the average position of the BT11 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm410302
Wind farm2110011.5
Wind turbine1006013.6
Battery storage31200236

MW in pipeline: pending, approved and under-construction capacity.

How Belfast decides solar, wind and battery applications

Belfast has 5 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.

All projects in Belfast

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near BT11, 8 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.