Battery Storage System Development in Lisburn (150 MW)

Battery Storage System Development in Lisburn is a 150 MW battery storage project in Lisburn and Castlereagh, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 30 January 2026, not yet built; the record was last updated on 24 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

150 MWbattery storage
approved, not builtstatus in REPD
24 February 2026record last updated
Lisburn and Castlereaghcouncil area

Planning timeline

DateStage
30 April 2024Application submitted
30 January 2026Planning permission granted
28 January 2031Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
150 MW
Status (REPD)
approved, not built
Record last updated
24 February 2026
Operator or applicant
Lisburn Energy Limited
Planning authority
Stockton-on-Tees
Planning application reference
LA05/2024/0401/F
Address (REPD)
On Lands Approximately 230m East of No 2 Moneybroom Road, Lisburn
Council area (by location)
Lisburn and Castlereagh
Time to decision
91 weeks
REPD reference
16478

Who decides

ApplicationsStockton-on-TeesUK
Decided applications (solar, wind, battery)3210,236
Refused0 (0%)19%
Solar refused0 of 2012%
Onshore wind refused0 of 345%
Battery storage refused0 of 916%
Median time from submission to decision16.4 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Ballinderry Road Solar Phase 1 (Lisburn)solar farm13.5operational1.4
Ballinderry Road Solar Phase 2 (Lisburn)solar farm7operational2.3
Former Maghaberry Airfieldsolar farm25.7operational5.2
Hillside Solar Farmsolar farm25.2operational5.6
Colinglen Road Batterybattery storage49.9application submitted7.6
Knockcairn Roadsolar farm6.5operational9.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.5273, -6.1152).