Ballinderry Road Solar Phase 2 (Lisburn) (7 MW)

Ballinderry Road Solar Phase 2 (Lisburn) is a 7 MW solar farm project in Lisburn and Castlereagh, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 20 February 2017; the record was last updated on 18 April 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7 MWsolar farm
operationalstatus in REPD
18 April 2017record last updated
Lisburn and Castlereaghcouncil area

Planning timeline

DateStage
19 May 2015Application submitted
14 October 2015Planning permission granted
1 July 2016Construction started
20 February 2017Operational

Project details

Technology
solar farm
Capacity
7 MW
Status (REPD)
operational
Record last updated
18 April 2017
Operator or applicant
RAD Energy One/ Island Green Power
Planning authority
Lisburn and Castlereagh
Planning application reference
LA05/2015/0157/F
Address (REPD)
Lands immediately north east o, Moneybroom Road, the junction of Ballinderry Rd, Lisburn
Council area (by location)
Lisburn and Castlereagh
Time to decision
21 weeks
REPD reference
5331

Who decides

Lisburn and Castlereagh has 9 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.

Other large projects within 10 km

ProjectTypeMWStatuskm
Ballinderry Road Solar Phase 1 (Lisburn)solar farm13.5operational0.9
Battery Storage System Development in Lisburnbattery storage150approved, not built2.3
Former Maghaberry Airfieldsolar farm25.7operational6.4
Hillside Solar Farmsolar farm25.2operational7.9
Colinglen Road Batterybattery storage49.9application submitted8.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.5132, -6.0883).