Knockcairn Road (6.5 MW solar farm)

Knockcairn Road is a 6.5 MW solar farm project in Antrim and Newtownabbey, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 March 2017; the record was last updated on 3 May 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.5 MWsolar farm
operationalstatus in REPD
3 May 2017record last updated
Antrim and Newtownabbeycouncil area

Planning timeline

DateStage
26 February 2014Application submitted
26 June 2014Planning permission granted
21 November 2016Construction started
15 March 2017Operational

Project details

Technology
solar farm
Capacity
6.5 MW
Status (REPD)
operational
Record last updated
3 May 2017
Operator or applicant
Lightsource Renewable Energy
Planning authority
Antrim and Newtownabbey
Planning application reference
T/2014/0066/F
Address (REPD)
20 Knockcairn Road, Crumlin
Council area (by location)
Antrim and Newtownabbey
Time to decision
17 weeks
REPD reference
1789

Who decides

ApplicationsAntrim and NewtownabbeyUK
Decided applications (solar, wind, battery)4010,236
Refused8 (20%)19%
Solar refused4 of 1412%
Onshore wind refused3 of 1945%
Battery storage refused1 of 716%
Median time from submission to decision48.1 weeks17.0 weeks
Appeals lodged / allowed7 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: Antrim and Newtownabbey, South Antrim.

Other large projects within 10 km

ProjectTypeMWStatuskm
Moira Roadsolar farm6.5operational1.5
Lands West of Belfast Roadsolar farm10operational4.5
Hillside Solar Farmsolar farm25.2operational5.5
South of Ballyscultysolar farm6.2refused on appeal7.1
Colinglen Road Batterybattery storage49.9application submitted8.8
Seegronan Wind Farm Extensionwind farm9approved, not built9.0
Seegronanwind farm13.8operational9.0
Battery Energy Storage System Facility in Antrimbattery storage50approved, not built9.1
Battery Storage System Development in Lisburnbattery storage150approved, not built9.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.6088, -6.1672).