Energy Projects Near You

Seegronan Wind Farm Extension (9 MW)

Seegronan Wind Farm Extension is a 9 MW wind farm project in Antrim and Newtownabbey, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 30 June 2017, not yet built; the record was last updated on 13 June 2019. REPD also records that the planning permission expired on 30 June 2022, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9 MWwind farm
approved, not builtmay be out of datestatus in REPD
13 June 2019record last updated
Antrim and Newtownabbeycouncil area

REPD also records that the planning permission expired on 30 June 2022, so the project may not go ahead in this form.

Planning timeline

DateStage
9 July 2013Application submitted
3 December 2014Appeal lodged
30 June 2017Planning permission granted
30 June 2017Appeal allowed
30 June 2022Permission expired

Project details

Technology
wind farm
Capacity
9 MW
Status (REPD)
approved, not built
Record last updated
13 June 2019
Operator or applicant
Seegronan Windfarm
Planning authority
Antrim and Newtownabbey
Planning application reference
J/2013/0187/F
Appeal reference
2014/A0180
Turbines
3
Address (REPD)
Killeter , Strabane , Co Tyrone
Council area (by location)
Antrim and Newtownabbey
Time to decision
207 weeks
REPD reference
3325

Who decides

ApplicationsAntrim and NewtownabbeyUK
Decided applications (solar, wind, battery)4010,236
Refused8 (20%)19%
Solar refused4 of 1412%
Onshore wind refused3 of 1945%
Battery storage refused1 of 716%
Median time from submission to decision48.1 weeks17.0 weeks
Appeals lodged / allowed7 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: Antrim and Newtownabbey, South Antrim.

Other large projects within 10 km

ProjectTypeMWStatuskm
Seegronanwind farm13.8operational<0.1
Altgolanwind farm17.5refused on appeal3.7
Battery Energy Storage System Facility in Antrimbattery storage50approved, not built7.4
Moira Roadsolar farm6.5operational7.6
South Antrim Solar Park - Phase 2solar farm39.5approved, not built8.0
South Antrim Solar Park - Phase 1solar farm6.5operational8.0
Knockcairn Roadsolar farm6.5operational9.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.6333, -6.3).