Energy Projects Near You

South Antrim Solar Park - Phase 2 (39.5 MW)

South Antrim Solar Park - Phase 2 is a 39.5 MW solar farm project in Antrim and Newtownabbey, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 25 April 2016, not yet built; the record was last updated on 29 July 2020. REPD also records that the planning permission expired on 25 April 2021, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

39.5 MWsolar farm
approved, not builtmay be out of datestatus in REPD
29 July 2020record last updated
Antrim and Newtownabbeycouncil area

REPD also records that the planning permission expired on 25 April 2021, so the project may not go ahead in this form.

Planning timeline

DateStage
30 June 2015Application submitted
25 April 2016Planning permission granted
25 April 2021Permission expired

Project details

Technology
solar farm
Capacity
39.5 MW
Status (REPD)
approved, not built
Record last updated
29 July 2020
Operator or applicant
Hadstone Energy
Planning authority
Antrim and Newtownabbey
Planning application reference
LA03/2015/0262/F
Site area
79.8 ha
Address (REPD)
Lands approx 550m South of, 99 Dublin Road, Antrim
Council area (by location)
Antrim and Newtownabbey
Time to decision
43 weeks
REPD reference
6829

Who decides

ApplicationsAntrim and NewtownabbeyUK
Decided applications (solar, wind, battery)4010,236
Refused8 (20%)19%
Solar refused4 of 1412%
Onshore wind refused3 of 1945%
Battery storage refused1 of 716%
Median time from submission to decision48.1 weeks17.0 weeks
Appeals lodged / allowed7 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: Antrim and Newtownabbey, South Antrim.

Other large projects within 10 km

ProjectTypeMWStatuskm
South Antrim Solar Park - Phase 1solar farm6.5operational<0.1
Battery Energy Storage System Facility in Antrimbattery storage50approved, not built1.4
Millar Farmsolar farm6operational5.3
Steeple Roadsolar farm25approved, not built6.1
South of Ballyscultysolar farm6.2refused on appeal6.5
Seegronanwind farm13.8operational8.0
Seegronan Wind Farm Extensionwind farm9approved, not built8.0
Elliot's Hill Wind Farmwind farm5operational8.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.6943, -6.2341).