Energy Projects Near You

Elliot's Hill Wind Farm (5 MW)

Elliot's Hill Wind Farm is a 5 MW wind farm project in Antrim and Newtownabbey, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 April 1995; the record was last updated on 29 August 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWwind farm
operationalstatus in REPD
29 August 2017record last updated
Antrim and Newtownabbeycouncil area

Planning timeline

DateStage
18 November 1993Application submitted
26 October 1994Planning permission granted
1 April 1995Operational

Project details

Technology
wind farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
29 August 2017
Operator or applicant
B9 Energy Services Ltd/ ScottishPower Renewables
Planning authority
Antrim and Newtownabbey
Planning application reference
not recorded
Turbines
10
Address (REPD)
Elliot's Hill Tildarg near Ballyclare County Antrim
Council area (by location)
Antrim and Newtownabbey
Time to decision
49 weeks
REPD reference
3106

Who decides

ApplicationsAntrim and NewtownabbeyUK
Decided applications (solar, wind, battery)4010,236
Refused8 (20%)19%
Solar refused4 of 1412%
Onshore wind refused3 of 1945%
Battery storage refused1 of 716%
Median time from submission to decision48.1 weeks17.0 weeks
Appeals lodged / allowed7 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: Antrim and Newtownabbey, South Antrim.

Other large projects within 10 km

ProjectTypeMWStatuskm
Drumadarragh Wind Farmwind farm8refused on appeal5.6
Steeple Roadsolar farm25approved, not built5.9
Corby Knowewind farm5operational6.8
Carncome, Lislunnan Roadbattery storage150approved, not built7.3
Battery Energy Storage System Development in Ballymenabattery storage79approved, not built7.4
Whappstown & Castlegore Windfarmswind farm23.1approved, not built7.5
Wolf Bog Wind Farmwind farm8.8operational7.7
South of Ballyscultysolar farm6.2refused on appeal7.7
Millar Farmsolar farm6operational7.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.7389, -6.119).