Battery Energy Storage System Development in Ballymena (79 MW)

Battery Energy Storage System Development in Ballymena is a 79 MW battery storage project in Antrim and Newtownabbey, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 20 October 2025, not yet built; the record was last updated on 10 November 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

79 MWbattery storage
approved, not builtstatus in REPD
10 November 2025record last updated
Antrim and Newtownabbeycouncil area

Planning timeline

DateStage
14 June 2024Application submitted
20 October 2025Planning permission granted
20 October 2030Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
79 MW
Status (REPD)
approved, not built
Record last updated
10 November 2025
Operator or applicant
Green Frog Power
Planning authority
South Antrim
Planning application reference
LA03/2024/0435/F
Address (REPD)
Lands Approximately 342m SE of Kells SubStn. and, Approximately 105m E. of 43, Kells, Ballymena
Council area (by location)
Antrim and Newtownabbey
Time to decision
70 weeks
REPD reference
16744

Who decides

ApplicationsAntrim and NewtownabbeyUK
Decided applications (solar, wind, battery)4010,236
Refused8 (20%)19%
Solar refused4 of 1412%
Onshore wind refused3 of 1945%
Battery storage refused1 of 716%
Median time from submission to decision48.1 weeks17.0 weeks
Appeals lodged / allowed7 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: Antrim and Newtownabbey, South Antrim.

Other large projects within 10 km

ProjectTypeMWStatuskm
Carncome, Lislunnan Roadbattery storage150approved, not built1.3
Kells Solar Farmsolar farm50application submitted1.4
Corby Knowewind farm5operational1.5
Whappstown & Castlegore Windfarmswind farm23.1approved, not built2.7
Wolf Bog Wind Farmwind farm8.8operational5.2
Steeple Roadsolar farm25approved, not built6.6
Drumadarragh Wind Farmwind farm8refused on appeal6.8
Cloghinarneywind farm13.8refused on appeal6.9
Elliot's Hill Wind Farmwind farm5operational7.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.8004, -6.162).