Cloghinarney (13.8 MW wind farm)

Cloghinarney is a 13.8 MW wind farm project in Mid and East Antrim, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 12 April 2016; the record was last updated on 4 May 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13.8 MWwind farm
refused on appealstatus in REPD
4 May 2016record last updated
Mid and East Antrimcouncil area

Planning timeline

DateStage
8 April 2011Application submitted
29 July 2014Refused by the planning authority
1 November 2014Appeal lodged
12 April 2016Appeal refused

Project details

Technology
wind farm
Capacity
13.8 MW
Status (REPD)
refused on appeal
Record last updated
4 May 2016
Operator or applicant
Cloghinarney Wind Farm
Planning authority
Mid and East Antrim
Planning application reference
G/2011/0155/F
Appeal reference
2014/A0089
Turbines
6
Address (REPD)
east of Ballynulto Road, Ballymena
Council area (by location)
Mid and East Antrim
Time to decision
173 weeks
REPD reference
4560

Who decides

ApplicationsMid and East AntrimUK
Decided applications (solar, wind, battery)3010,236
Refused5 (17%)19%
Solar refused0 of 612%
Onshore wind refused5 of 2245%
Battery storage refused0 of 216%
Median time from submission to decision45.2 weeks17.0 weeks
Appeals lodged / allowed5 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Douglas Topwind farm51application withdrawn1.9
Whappstown & Castlegore Windfarmswind farm23.1approved, not built5.3
Kells Solar Farmsolar farm50application submitted5.5
Carnalbanagh Windfarmwind farm21application submitted5.7
Wolf Bog Wind Farmwind farm8.8operational5.8
Battery Energy Storage System Development in Ballymenabattery storage79approved, not built6.9
Carncome, Lislunnan Roadbattery storage150approved, not built8.0
Corby Knowewind farm5operational8.4
Drumadarragh Wind Farmwind farm8refused on appeal8.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.854, -6.1076).