Energy Projects Near You

Kells Solar Farm (50 MW)

Kells Solar Farm is a 50 MW solar farm project in Mid and East Antrim, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 26 June 2015, no decision recorded; the record was last updated on 5 February 2016. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWsolar farm
application submittedmay be out of datestatus in REPD
5 February 2016record last updated
Mid and East Antrimcouncil area

The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.

Planning timeline

DateStage
26 June 2015Application submitted

Project details

Technology
solar farm
Capacity
50 MW
Status (REPD)
application submitted
Record last updated
5 February 2016
Operator or applicant
Elgin Energy EsCo
Planning authority
Antrim and Newtownabbey
Planning application reference
LA03/2015/0234/F
Address (REPD)
Lands Extending NW And SE Of, Whappstown Road, Moorfields, Castlegore, Ballymena
Council area (by location)
Mid and East Antrim
REPD reference
6012

Earlier applications for this site

ApplicationMWSubmittedOutcome
Govals Wind Farm 12/00570/EIAL4.87 June 2012refused 15 May 2013
Kells Solar Farm LA01/2015/0980/F2527 November 2015replaced by a revised application

Who decides

ApplicationsAntrim and NewtownabbeyUK
Decided applications (solar, wind, battery)4010,236
Refused8 (20%)19%
Solar refused4 of 1412%
Onshore wind refused3 of 1945%
Battery storage refused1 of 716%
Median time from submission to decision48.1 weeks17.0 weeks
Appeals lodged / allowed7 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: Antrim and Newtownabbey, South Antrim.

Other large projects within 10 km

ProjectTypeMWStatuskm
Battery Energy Storage System Development in Ballymenabattery storage79approved, not built1.4
Whappstown & Castlegore Windfarmswind farm23.1approved, not built1.7
Carncome, Lislunnan Roadbattery storage150approved, not built2.7
Corby Knowewind farm5operational2.9
Wolf Bog Wind Farmwind farm8.8operational4.3
Cloghinarneywind farm13.8refused on appeal5.5
Drumadarragh Wind Farmwind farm8refused on appeal6.4
Douglas Topwind farm51application withdrawn6.4
Steeple Roadsolar farm25approved, not built8.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.8098, -6.147).