Energy Projects Near You

Solar, wind and battery projects near Ballymena (BT42)

18 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of BT42 (Mid and East Antrim): 4 are waiting for a planning decision, 9 approved but not yet running, 4 operational. The largest live scheme is Carncome, Lislunnan Road (150 MW battery storage, approved on 10 April 2026, not yet built), 9.1 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18projects within 10 km
4awaiting a decision
9approved, not running
4operational

Projects within 10 km of BT42

Projects of 1 MW and more (10)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Solar PV Development in Ballymenasolar farmsolar farm2.5approved, not builtupdated Sep 2024Apr 2024granted Aug 2024Sep 2024Mid and East Antrim1.3
Solar PV Energy Development in Ballymenasolar farmsolar farm2approved, not builtupdated Sep 2024Apr 2024granted Aug 2024Sep 2024Mid and East Antrim1.3
Solar Farm Development in Ballymenasolar farmsolar farm3.5approved, not builtupdated May 2025Dec 2024granted Apr 2025May 2025Mid and East Antrim3.5
Ballygarvey Roadsolar farmsolar farm13operationalupdated Jun 2018Dec 2015granted Sep 2016Jun 2018Mid and East Antrim3.6
Ballymena Wind Park Limitedwind farmwind farm4.7operationalupdated Aug 2013Jul 2009granted Apr 2010Aug 2013Mid and East Antrim3.9
The Michelin Tyre Factory - Ballymenawind farmwind farm4.6operationalupdated Apr 2013Jul 2009granted Feb 2010Apr 2013Mid and East Antrim5.3
Carncome, Lislunnan Roadbattery storagebattery storage150approved, not builtupdated May 2026Jul 2025granted Apr 2026May 2026Antrim and Newtownabbey9.1
Battery Energy Storage System Development in Ballymenabattery storagebattery storage79approved, not builtupdated Nov 2025Jun 2024granted Oct 2025Nov 2025Antrim and Newtownabbey9.5
Corby Knowewind farmwind farm5operationalupdated May 2017Nov 2006granted Jan 2013May 2017Antrim and Newtownabbey9.5
Kells Solar Farmsolar farmsolar farm50application submitted may be out of dateupdated Feb 2016Jun 2015—Feb 2016Mid and East Antrim9.6
Smaller schemes under 1 MW, mostly rooftop solar (8)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Solar Farm Development in Ballymenasolar farmsolar farm—application submittedupdated Nov 2024Sep 2024—Nov 2024Mid and East Antrim3.5
Woodside Roadwind turbinewind turbine0.3approved, not built may be out of dateupdated Feb 2020Dec 2019granted Oct 2020Feb 2020Mid and East Antrim3.9
93 Caddy Roadwind turbinewind turbine0.8approved, not builtupdated Dec 2023Jan 2023granted Dec 2023Dec 2023Mid and East Antrim6.5
Wind Turbine Development in Ballymenawind turbinewind turbine—application submittedupdated May 2025Mar 2025—May 2025Mid and East Antrim6.6
85 Deerfin Road, Ballymenawind turbinewind turbine0.2refusedupdated Sep 2024Apr 2023refused Sep 2024Sep 2024Mid and East Antrim7.3
Kells Substationbattery storagebattery storage—approved, not built may be out of dateupdated Apr 2020Oct 2018granted Nov 2019Apr 2020Antrim and Newtownabbey9.1
Garvaghy Roadwind turbinewind turbine—application submitted may be out of dateupdated Dec 2022Oct 2020—Dec 2022Mid and East Antrim9.3
Carmagrim Roadwind turbinewind turbine0.2approved, not built may be out of dateupdated Jun 2020Jan 2020granted Apr 2021Jun 2020Mid and East Antrim9.7

Distance from the average position of the BT42 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm6231058
Wind farm300300
Wind turbine623011.4
Battery storage30300229

MW in pipeline: pending, approved and under-construction capacity.

How Mid and East Antrim decides solar, wind and battery applications

ApplicationsMid and East AntrimUK
Decided applications (solar, wind, battery)3010,236
Refused5 (17%)19%
Solar refused0 of 612%
Onshore wind refused5 of 2245%
Battery storage refused0 of 216%
Median time from submission to decision45.2 weeks17.0 weeks
Appeals lodged / allowed5 / 1—

All projects in Mid and East Antrim

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near BT42, 5 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.