Energy Projects Near You

Solar, wind and battery projects near Magherafelt (BT45)

15 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of BT45 (Mid Ulster): 6 are waiting for a planning decision, 5 approved but not yet running, 3 operational. The largest live scheme is Cullion wind farm (25 MW wind farm, application submitted on 19 July 2019, no decision recorded; REPD status may be out of date), 6.2 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15projects within 10 km
6awaiting a decision
5approved, not running
3operational

Projects within 10 km of BT45

Projects of 1 MW and more (5)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Magherafeltwind turbinewind turbine1operationalupdated Jul 2016Jul 2009granted Nov 2010Jul 2016Mid Ulster1.2
Cullion wind farmwind farmwind farm25application submitted may be out of dateupdated Sep 2019Jul 2019—Sep 2019Mid Ulster6.2
Draperstown (Brackagh) Wind Farmwind farmwind farm6operationalupdated Apr 2017Feb 2009granted Jun 2010Apr 2017Mid Ulster7.2
Crockandunwind farmwind farm15operationalupdated Jul 2017Jan 2010granted Nov 2012Jul 2017Mid Ulster8.8
Dirnan Road Wind Turbinewind turbinewind turbine3refused on appealupdated Aug 2016Jul 2014refused Jun 2015Aug 2016Mid Ulster9.7
Smaller schemes under 1 MW, mostly rooftop solar (10)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Drumard Road, Gulladuffsolar farmsolar farm—approved, not builtupdated Jun 2024Apr 2023granted Jun 2024Jun 2024Mid Ulster7.7
Wind Turbine Development in Moneymorewind turbinewind turbine0.2application submittedupdated Apr 2025Feb 2025—Apr 2025Mid Ulster8.1
PV Panels Development in Tobermorerooftop solarrooftop solar—approved, not builtupdated Dec 2024Jun 2024granted Aug 2024Dec 2024Mid Ulster8.7
PV Panels Development in Tobermorerooftop solarrooftop solar—approved, not builtupdated Dec 2024Jun 2024granted Aug 2024Dec 2024Mid Ulster8.7
Airfield Road, The Creaghwind turbinewind turbine0.1approved, not builtupdated Jan 2023Aug 2021granted Dec 2022Jan 2023Mid Ulster8.8
Drumard Road (repowering)wind turbinewind turbine0.5application submitted may be out of dateupdated Jun 2019Dec 2018—Jun 2019Mid Ulster9.0
Solar PV Panels Installation in Toomerooftop solarrooftop solar—approved, not builtupdated Nov 2024Sep 2024granted Oct 2024Nov 2024Mid Ulster9.5
Drumard Road and Cullion Roadwind turbinewind turbine—application submitted may be out of dateupdated Jun 2023Apr 2023—Jun 2023Mid Ulster9.7
Drumard Road and Cullion Roadwind turbinewind turbine—application submitted may be out of dateupdated Jun 2023Apr 2023—Jun 2023Mid Ulster9.7
Drumard Road and Cullion Roadwind turbinewind turbine—application submitted may be out of dateupdated Jun 2023Apr 2023—Jun 2023Mid Ulster9.7

Distance from the average position of the BT45 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm101000
Rooftop solar303000
Wind farm3102025
Wind turbine851110.9

MW in pipeline: pending, approved and under-construction capacity.

How Mid Ulster decides solar, wind and battery applications

ApplicationsMid UlsterUK
Decided applications (solar, wind, battery)4910,236
Refused8 (16%)19%
Solar refused0 of 912%
Onshore wind refused8 of 3345%
Battery storage refused0 of 716%
Median time from submission to decision68.9 weeks17.0 weeks
Appeals lodged / allowed5 / 1—

All projects in Mid Ulster

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near BT45, 5 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.