Energy Projects Near You

Crockandun (15 MW wind farm)

Crockandun is a 15 MW wind farm project in Mid Ulster, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 9 March 2017; the record was last updated on 28 July 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15 MWwind farm
operationalstatus in REPD
28 July 2017record last updated
Mid Ulstercouncil area

Planning timeline

DateStage
8 January 2010Application submitted
30 November 2012Planning permission granted
15 January 2016Construction started
9 March 2017Operational

Project details

Technology
wind farm
Capacity
15 MW
Status (REPD)
operational
Record last updated
28 July 2017
Operator or applicant
Brookfield Renewable Energy Group
Planning authority
Mid Ulster
Planning application reference
H/2010/0009/F
Turbines
6
Address (REPD)
approximately 450m west south-west of junction of Cullion Road and Drumard Road, Draperstown, Magherafelt.
Council area (by location)
Mid Ulster
Time to decision
151 weeks
REPD reference
4156

Who decides

ApplicationsMid UlsterUK
Decided applications (solar, wind, battery)4910,236
Refused8 (16%)19%
Solar refused0 of 912%
Onshore wind refused8 of 3345%
Battery storage refused0 of 716%
Median time from submission to decision68.9 weeks17.0 weeks
Appeals lodged / allowed5 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Cullion wind farmwind farm25application submitted3.2
Ballynagilly Renewable Energy Projectwind farm18.4appeal withdrawn5.8
Beltonanean Wind Farmwind farm12appeal withdrawn8.8
Draperstown (Brackagh) Wind Farmwind farm6operational9.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.7395, -6.7719).